Event ID	Change ID	Event date	Event type	Direction	Source reference	Factual summary	Linked price revision	Decision result	Decision amount CAD	Decision reference	Recorded by	Next action	Target date
EVT-017-01	CHG-017	2026-08-03	Technical question	Received	RFI-041	Level 3 routing conflict reported					M. Tremblay	Obtain written direction	2026-08-05
EVT-017-02	CHG-017	2026-08-05	Direction	Received	WD-014	Pipe reroute requested in writing					M. Tremblay	Prepare the price	2026-08-08
EVT-017-03	CHG-017	2026-08-08	Price submitted	Sent	EST-017-R1	Revision R1 submitted	CHG-017-R1	In negotiation	17000		M. Tremblay	Revise after discussion	2026-08-15
EVT-017-04	CHG-017	2026-08-15	Revised price	Sent	EST-017-R2	Revision R2 submitted	CHG-017-R2	Pending decision	15400		M. Tremblay	Obtain the written decision	2026-08-21
EVT-017-05	CHG-017	2026-08-21	Decision	Received	CO-012	Revision R2 approved per the received reference	CHG-017-R2	Approved	15400	CO-012	S. Nguyen	Create the billing link	2026-08-22
EVT-018-01	CHG-018	2026-08-18	Site instruction	Received	SI-028	Seismic supports require clarification					S. Nguyen	Clarify the scope	2026-08-20